How Much Waste Factor Should You Add to Building Materials?

By the EnoughToBuy teamUpdated November 13, 20266 min readSources and assumptions

Quick answer: Most building projects need about 5 to 15 percent extra material. Ten percent is the common starting point for flooring, tile, drywall, paint, roofing and decking, and about 5 percent is typical for simpler materials like insulation, sod and block. Complicated layouts, such as diagonal tile, herringbone floors and roofs with many valleys, need 15 percent or more.

Waste is the part of the order that never ends up on the finished surface. It is not a sign that you made a mistake. It is a normal part of working with materials that come in fixed sizes, have to be cut to fit and sometimes arrive damaged. Getting the waste factor right is the difference between a job that finishes on schedule and a job that stops while you wait for another delivery. The figures below come from calculators such as the flooring calculator.

Try itFlooring: enter your own sizes
You would buy10boxes
  • Flooring (20 ft²/box)10 boxes
Open the full calculator with more options

What the waste factor covers

When you add 10 percent, that percentage is paying for several different things at once:

  • Cuts. Every row of flooring, every course of shingles and every sheet of drywall ends at a wall or an edge, where it has to be cut. The offcut is sometimes usable and often not.
  • Defects and damage. A few boards or tiles will arrive cracked, warped or chipped, and some will be damaged during handling.
  • Mistakes. Everyone cuts a piece wrong now and then. A waste allowance means one mistake does not stop the job.
  • Layout and pattern. Patterns need matching, and a pattern repeat can waste material at each edge.
  • Spillage and leftovers. Paint stays in the tray, concrete stays in the wheelbarrow and gravel compacts under the tamper.
  • Future repairs. A small amount left over is a sample you can use to repair damage years later, when the product may no longer be sold.
Solid blocks are the boxes the floor needs, striped blocks are the waste allowance, and the empty block is what is left after rounding up to whole boxes.

Waste factors by material

The calculators on this site start with these allowances. They are editable defaults based on common contractor guidance, not official standards, and they assume a fairly simple job.

MaterialDefault waste
Flooring (boxes)10%
Tile10%
Drywall10%
Paint10%
Wallpaper10%
Roofing shingles10%
Siding10%
Deck boards10%
Concrete slab10%
Concrete columns and footings10%
Gravel and mulch10%
Baseboard and trim10%
Retaining wall blocks10%
Block and brick5%
Sod5%
Insulation5%

You can change the number in each calculator. If your supplier or installer gives you a different figure for your product, use that figure.

How the waste factor changes the number you buy

The effect looks small as a percentage but can be large in whole units, because you round up to a full box, bundle or sheet.

Flooring example: 200 square feet

At 20 square feet per box, a 200 square foot floor needs these quantities:

WasteSquare feet to buyBoxes
0%20010
5%21011
10%22011
15%23012

Going from no waste to 15 percent adds 2 boxes, which is a reasonable price for a job you can finish in one trip. The default of 10 percent gives 11 boxes. See the full guide on how many boxes of flooring you need for 200 square feet.

Tile example: a 10 ft by 8 ft floor

Tile is cut at the edges, and tiles break when you cut them, so tile usually needs more waste than flooring that is easy to cut.

WasteBoxes of tile
5%9
10%9
15%10
20%10

Roofing example: a 40 ft by 28 ft house

Roof waste depends on the number of hips, valleys and obstacles. A simple gable roof is near the low end.

WasteBundles of shingles
5%45
10%47
15%49
20%51

The guide on how many bundles of shingles for a roof shows how the pitch changes the surface area.

Drywall example: a 12 ft by 10 ft room

Waste4x8 sheets for walls and ceiling
5%16
10%17
15%17

How to choose your own waste factor

Start with the default for the material, then adjust for your job.

SituationGuidance
Simple, rectangular room or roof, straight layoutStart at 5 to 10 percent
Many corners, doors, windows or obstaclesAdd 5 percentage points
Diagonal layout (flooring or tile)Plan for 10 to 15 percent or more
Herringbone or complex patternPlan for 15 to 20 percent or more
Large-format or natural stone tileAsk your installer, since breakage is higher
Complex roof with hips, valleys and dormersPlan for 15 percent or more
First time doing this kind of workGo to the higher end of the range
Easy to get more later, and the product does not vary by lotYou can use less

These are common rules of thumb, not requirements. The best source is the installation guide for your product, and the second best is an experienced installer.

Waste versus leftovers

Waste and leftovers are different. Waste is the material you lose to cutting and mistakes. Leftovers are the unopened boxes, bundles or sheets you have after the job. The waste allowance is meant to cover waste, and it often leaves you with leftovers because you cannot buy half a box.

Leftovers are not a bad thing. Keep them for repairs. Flooring, tile and shingles are made in production lots that may differ in color, and your leftovers are the only guaranteed match. Store them dry and flat, and label the box with the room and the date.

When less waste is fine

You can use a lower waste factor when:

  • The surface is a simple rectangle with no obstacles.
  • The product is easy to cut and the offcuts are reusable, as with a long run of baseboard or a long wall of drywall.
  • The material is sold in small increments, such as bulk gravel by the half yard.
  • You can easily return unopened boxes, and you have confirmed the store's policy in writing.

Even then, be careful about cutting it too close. A few extra units usually cost less than a delayed job.

When more waste is wise

Raise the factor when:

  • You are using a pattern that has to match across pieces.
  • The material is fragile, like large tiles or glass.
  • You are a beginner and expect mistakes.
  • The product is discontinued or made to order, so you cannot buy more later.
  • The surface has many angles or curves.

Common mistakes with waste

  1. Applying waste twice. If you add 10 percent to the area, do not add it again to the box count. The calculators apply it once.
  2. Forgetting to round up. Round to whole boxes, bundles or sheets after you add waste.
  3. Using one factor for everything. Paint, flooring and roofing behave differently. Use the number for the material.
  4. Treating waste as optional. A zero-waste order is nearly always short.
  5. Throwing away leftovers. Keep a few pieces for repairs.
  6. Ignoring the supplier's advice. Many product guides recommend a specific percentage.

Frequently asked questions

How much waste should I add to flooring?

Ten percent is a common starting point for a straight installation. For diagonal layouts, plan for 10 to 15 percent. Check the installation guide for your flooring.

How much extra tile should I buy?

Ten percent is common for straight layouts, and 15 to 20 percent for diagonal or complex layouts, large tiles and natural stone. Tile can break when it is cut, so extra is useful.

How much extra drywall should I buy?

Ten percent is a common allowance. Simple rooms may need less, and rooms with many openings or angles need more.

How much waste for roofing shingles?

Ten percent is common for a simple gable roof. Roofs with hips, valleys and dormers usually need 15 percent or more.

Is 10 percent waste enough?

For many simple projects, yes. For complicated jobs, patterns and fragile materials, it may not be.

Should I buy extra for future repairs?

If the product may be discontinued or varies by production lot, yes. One extra box of flooring or tile can save a repair later.

Do I add waste before or after I divide by the coverage?

Add it before. Multiply the area by one plus the waste, divide by the coverage per unit, then round up.

How Much Waste Factor Should You Add to Building Materials?
Save or share this answer.

Sources and assumptions

These are the settings behind every number above. Verified figures link to a source. Editable defaults are common rules of thumb: change them in the calculator to match your product and your site.

SettingValueStatusSource
flooring waste10 %Editable defaultcontractor rule of thumb, editable
tile waste10 percentEditable defaultContractor rule of thumb for straight layouts. Diagonal and pattern layouts need more. Not verified.
drywall waste10 %Editable defaultcontractor rule of thumb, editable
paint waste10 %Editable defaultcontractor rule of thumb, editable
roofing waste10 percentEditable defaultContractor rule of thumb for simple roofs. Complex roofs need more. Not verified.
deck waste10 percentEditable defaultContractor rule of thumb for deck boards. Not verified.
concrete slab waste0.1 fractionEditable defaultCommon contractor rule of thumb (about 5-10% for spillage and uneven ground). Editable by the user. Not an official figure.
gravel mulch waste10 %Editable defaultcontractor rule of thumb, editable
trim waste10 percentEditable defaultContractor rule of thumb for miter cuts. Not verified.
insulation waste5 percentEditable defaultContractor rule of thumb for batt insulation. Not verified.
sod waste5 percentEditable defaultContractor rule of thumb for cuts. Not verified.
block waste5 percentEditable defaultContractor rule of thumb for breakage and cuts. Not verified.
flooring box coverage20 ft2/boxEditable defaultmanufacturer label typical